Process Analysis project

Once you have registered and logged into Blue Prism Process Intelligence, complete the following steps:

  1. Click the Upload your data button on the Welcome page or select Project > Upload data.

  2. Select a file for upload.
  3. At the Map columns step, drag the timeline stamps on to their corresponding columns. For example, drag the Timeline ID mark into the TimelineID column. See Mapping Data for details.
  4. To complete the upload and start analyzing the data, click the Confirm and Start Upload button.

    See Data upload for alternative ways of uploading data. See Data requirements for the requirements that your uploaded data must meet.

  5. Click the Go to timeline set button to see the overview of the uploaded data.

Once the data is loaded, it will be analyzed and the Overview page will open, displaying an overview of the uploaded data, the analysis results, and information about the timelines. See Overview page for details.

Processed data can be analyzed using any of the built-in analysis modules. See Analysis modules for details.